Woodman Road Multi-Use Trail

Project Status: Underway - Construction

Estimated Cost: $345,000
Start Date: February 2022
Estimated End Date: May 2022

Magisterial District:   Brookland   Fairfield  


The County of Henrico will construct a 0.6 mile long, 12-foot wide asphalt multi-use trail along the west side of Woodman Road Extended between Greenwood Road and the River Mill Development. 

 

 

Estimated Schedule: 

  • Design is complete. 
  • Right-of-way has been acquired. 
  • Utility relocations completed. 
  • Construction is underway. 
  • Project completed in May 2022. 