Woodman Road Extension and Roundabout Project

Project Status: Underway - Design

Estimated Cost: $6.8 million total
Start Date: Fall 2017
Estimated End Date: December 2019

Magisterial District:   Brookland   Fairfield  


The extension of Woodman Road is designated a Proposed Minor Arterial roadway on the 2026 Major Thoroughfare Plan.  The project design will extend Woodman Road from Greenwood Road to Jeb Stuart Parkway.  A 2-lane divided roadway will be constructed with a shared-use pedestrian path that will connect the infrastructure improvements to be built with the River Mill Development.  Additional traffic control  will be implemented at the intersection of Greenwood Road and Woodman Road.  The project will relieve traffic congestion, and improve improve vehicular and pedestrian connectivity in the area.  For more information, you can view the brochure that was available at the Citizen Information Meeting.

 

Estimated Schedule

  • Design is underway
  • Right-of-way acquisition is anticipated to begin Winter 2017/2018
  • Advertisement for Construction is anticipated for Summer 2018
  • Construction is anticipated to begin Fall 2018
  • Project completion is anticipated  for December 2019

Woodman Road Roundabout Video

Progress to Date

  • A Citizen Information Meeting will be held on May 9, 2018 at Greenwood Elementary School to collect feedback on the roundabout included in this project.  
  • There was a Citizen Information Meeting held on October 3, 2017 to present information and collect feedback for this project. 

Contact Us

Steve Bandura
(804) 501-5985
ban03@henrico.us


Public Works

Henrico Department of Public Works
4301 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Category