Fall Line Trail – Longdale Phase

Project Status: Underway - Design

Estimated Cost: $25 million
Start Date: September 2024
Estimated End Date: September 2026

Magisterial District:   Fairfield  


The County of Henrico will be constructing approximately 3.2 miles of a 12-foot-wide asphalt multi-use trail from the intersection of Parham Road and Cleveland Street to the new Woodman Road Extension. This work will be a part of The Fall Line Trail, a 43-mile north-south paved trail that will connect Ashland to Petersburg. Additional design features for the Longdale Phase may include but are not limited to:

  • Pedestrian accommodations at the intersections of Cleveland Street with Hungary Road and Parham Road.
  • A trailhead parking lot within the median between Athens Road and Blackstone Avenue.
  • Trailhead parking improvements and a picnic and leisure area within the Longdale Recreation Center

 

Estimated Schedule: 

·      Design currently underway.

·      Right-of-way acquisition is anticipated to begin in February 2023

·      Utility relocation is anticipated to begin October 2023

·      Advertisement for construction is anticipated in July 2024

·      Construction is anticipated to begin in Septermber 2024

·      Project completion is anticipated in September 2026