Shrader Road Sidewalk

Project Status: Underway - Design

Estimated Cost: $1.9 million
Start Date: May 2025
Estimated End Date: January 2026

Magisterial District:   Brookland  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

  • Approximately 2,000-ft of sidewalk along both sides of Shrader Road from E. Parham Rd to Eunice Dr. 
  • Associated ADA ramps across private entrances. 
  • Striped pedestrian crossing at Eunice Drive. 

Estimated Schedule: (Month Year) 

  • Design is anticipated to start January 2023. 
  • Right-of-way acquisition is anticipated to commence November 2023. 
  • Utility relocation is anticipated to commence April 2024. 
  • Advertisement for construction is anticipated March 2025. 
  • Construction is anticipated to commence May 2025. 

Progress to Date

  • Survey has been completed.
  • 30% plans have been completed.

Contact Us

Michael Elander
(804) 501-4624
ela013@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon

Translate