Sadler Road Improvements

Project Status: Underway - Right of Way Acquisition

Estimated Cost: $ 30.6 million total
Start Date: August 2023
Estimated End Date: August 2025

Magisterial District:   Three Chopt  


The County of Henrico will be constructing the following improvements:

  • A 1.9-mile section of Sadler Road between Dominion Boulevard and Cedar Forest Road will be widened and the alignment improved.
  • The roadway will consist of two lanes, one in each direction with a center left turn lane, curb and gutter, and improved drainage.
  • A shared use path for pedestrians and bicyclists will be constructed on the east side of the new roadway.
  • The segment between Ireland Lane and Sadler Grove Road will be on a new alignment.
  • Roundabouts are proposed at the intersections of Sadler Road and Innslake Drive, and at Sadler Road and Sadler Grove Road.

Estimated Schedule

  • Design is underway.
  • Right-of-way acquisition began June 2020.
  • Utility relocation is anticipated to begin February 2022.
  • Advertisement for construction is anticipated April 2023.
  • Construction is anticipated to begin August 2023.
  • Project completion is anticipated August 2025.

 

Progress to Date


Contact Us

Kevin Newcomb
(804) 501-5532
new038@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Category


 
Google Translate Icon

Translate