Creighton Road Improvements

Project Status: Underway - Construction

Estimated Cost: $8.4 million total
Start Date: May 2016
Estimated End Date: 2020

Magisterial District:   Fairfield   Varina  


Creighton Road Improvements between North Laburnum Avenue and the city of Richmond limits began Monday, May 19. Improvements include replacement of the narrow bridge by Glenwood Golf Club.  The focus of this first 0.5 mile segment between Caddie Lane and Stone Dale Drive, will be road widening and realignment and the construction of a new bridge structure.  A wider, two-lane bridge will be installed to the north of the existing, one-lane structure, which spans the creek. The bridge approaches will also be improved.

Creighton Road is closed to through-traffic from Caddie Lane to Stone Dale Drive until completion of the project. A detour will direct motorists on Creighton Road around the work zone by way of Gordons Lane, Nine Mile Road and Laburnum Avenue. Access to Glenwood Golf Club will be allowed from the western side of the work zone, toward Richmond City.  Residents inside the work zone will have access to their properties throughout construction.

Final Completion: February 2017

Project Cost: $3.45 million

The next segment of the Creighton Road Improvements will be to construct a 0.4 mile 4-lane divided roadway between Sandy Lane and E. Laburnum Avenue. It includes curb-and-gutter, drainage improvements, sidewalk on both sides of the road, and realigning the intersection with Dabbs House Road to a point approximately 500 feet west of the current intersection.   

Design is  70% complete and anticipated for completion June 2017

Right-of-way acquisition is anticipated for completion June 2018

Utility relocation is anticipated for completion December 2018

Advertise for Construction in Summer/Fall 2019

Final Completion: 2020

Project Cost: $4.95 million

Progress to Date

  • As of February 6, 2017 the bridge deck and new roadway base pavement have been placed.  However, the road will not open until the surface course is placed.  This is anticipated to be completed May 2017.
  • As of September 21, 2016, the new Creighton Road bridge structure is now being installed.  Please check back regularly for new progress pictures, and updates.
  • Work to replace the bridge located on Creighton Road between Laburnum Avenue and the Richmond corporate limits began on May 16, 2016.  Creighton Road is closed to through traffic between Caddie Lane and Stone Dale Drive until the project is completed. A map detailing the detour around the bridge is available.  

Contact Us

Public Works

Henrico Department of Public Works
4301 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Category