Creighton Road Improvements – Sandy Lane to Laburnum Avenue

Project Status: Underway - Design

Estimated Cost: $8.4 million total
Start Date: May 2016
Estimated End Date: 2020

Magisterial District:   Fairfield   Varina  


 

The Creighton Road Improvements between Sandy Lane and Laburnum Avenue will realign the existing roadway to include a 0.4 mile 4-lane divided roadway with sidewalks on both sides of the road.  The road realignment includes relocating the Dabbs House Road intersection approximately 500 feet west of the current intersection, improving the intersection at Sandy Lane, and eliminating difficult to navigate curves in the roadway.  

Design is  90% complete and anticipated for completion February 2018

Right-of-way acquisition is anticipated for completion June 2018

Utility relocation is anticipated for completion December 2018

Advertise for Construction in Winter/Spring 2019

Final Completion: 2020

Project Cost: $4.95 million

Progress to Date

  • The Creighton Road Bridge is complete as of March 3, 2017, and open for traffic.

Contact Us

Margaret-Anne Hilliard
(804) 501-4244
hil66@henrico.us


Public Works

Henrico Department of Public Works
4301 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Category