Ridge Road Sidewalk, Phase 1

Project Status: Underway - Construction

Estimated Cost: $740,000
Start Date: January 2024
Estimated End Date: July 2024

Magisterial District:   Tuckahoe  


The County of Henrico will be constructing approximately 1,920 feet of 5-foot-wide sidewalk with a 2-foot-wide grass strip along the southwest side of Ridge Road between Old Providence Circle and North Ridge Road. In addition, approximately 260 feet of new curb and gutter will be constructed between Ziontown Road and the adjacent business parcel. 

Estimated Schedule

  • Design is complete.
  • Right-of-way acquisition is complete.
  • Utility relocations are complete.
  • Advertisement for construction is completed.
  • Construction began January 2024.
  • Project completion is anticipated:  July 2024.

Progress to Date

  • A Public Hearing to discuss project details will be held on Wednesday, June 9, 2021 at the Tuckahoe Library from 5:30 PM to 6:30 PM.  

Contact Us

Michael Elander
(804) 501-4624
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate