Mayland/Parham Thru Cut

Project Status: Underway - Design

Estimated Cost: $550,000
Start Date: 2025
Estimated End Date: 2025

Magisterial District:   Three Chopt  


  • The County of Henrico will be constructing a raised directional concrete island at the intersection of Parham Rd and Mayland Drive to eliminate the thru movement at that intersection. The goal is to increase operations and safety at the intersection. 

Estimated Schedule: (Month Year) 

  • Design is underway 
  • Right-of-way acquisition is anticipated in 2nd Quarter, 2024
  • Utility relocation is anticipated in 3rd Quarter, 2024
  • Advertisement for construction is anticipated in 2025
  • Construction is anticipated to begin in 2025

Contact Us

Ashley Fisher
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate