Ridgefield Parkway Sidewalk

Project Status: Underway - Design

Estimated Cost: $1.2 million total
Start Date: Fall 2017
Estimated End Date: 2018

Magisterial District:   Three Chopt   Tuckahoe  


Henrico County is constructing approximately 1.0 mile of sidewalk on Ridgefield Parkway between Pump Road and Gaskins Road. The design will evaluate placement of a 4’ wide sidewalk with a 2’ utility strip, or another acceptable alternative. Crosswalk and pedestrian signals will be designed and installed as part of the project.

Estimated Schedule

  • Design is 90% complete
  • Right-of-way acquisition is anticipated to begin in June 2017
  • Utility relocation is anticipated to begin in June 2017
  • Advertisement for construction is anticipated for September 2017
  • Project completion is anticipated in 2018

Progress to Date

  • Design is now 90% complete, and is scheduled to be fully complete by December 2016.
  • A Citizen Information Meeting for this project was held on January 19, 2016.

Contact Us

Public Works

Henrico Department of Public Works
4301 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775