Winfrey Road Pedestrian Improvements

Project Status: Completed

Estimated Cost: $137,773
Start Date: July 2023
Actual End Date: September 2023

Magisterial District:   Brookland   Fairfield  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed, including: 

 

  • Accommodations for pedestrians from Winfrey Road on the south side of Woodman Road to safely access the north side of Winfrey Road and/or the Fall Line Trail.    

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is anticipated to begin 06/2023.
  • Utility relocation is not anticipated. 
  • Advertisement for construction is not anticipated. 
  • Construction is anticipated to begin 09/2023. 

Contact Us

Ryan Levering
(804) 278-7505
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate