Tuckahoe Park Stream Restoration

Project Status: Underway - Design

Estimated Cost: $4.2 million total
Start Date: December 2020
Estimated End Date: December 2021

Magisterial District:   Three Chopt  


The Tuckahoe Park Stream Restoration project will restore approximately 1,640 linear feet of stream along Upham Brook that extends from Parham Road to Mayland Drive between Comet Drive and the Parham Professional Park.  

Estimated Schedule

  • Design began August 2017
  • Right-of-way acquisition is anticipated to begin July 2018
  • Utility relocation is anticipated to begin July 2018
  • Advertisement for Construction is anticipated July 2020
  • Construction is anticipated to begin December 2020
  • Project completion is anticipated in December 2021

Progress to Date


Contact Us

Michael Aust
(804) 501-4019
aus019@henrico.us


Public Works

Henrico Department of Public Works
4301 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon

Translate