Thalbro St Sidewalks

Project Status: Underway - Design

Estimated Cost: $900,000
Start Date: December 2024
Estimated End Date: December 2025

Magisterial District:   Brookland  


The County of Henrico will be constructing accommodations to increase pedestrian access and connectivity. The following improvements will be constructed:  

  • Approximately 900 feet of sidewalk along the northern side of Thalbro Street between Staples Mill Road (Route 33) and Maywill Street.
  • Additional ADA curb ramps and pedestrian crosswalks on the south and west legs at the intersection of  Thalbro Street and Maywill Street. 
  •  

Estimated Schedule: (Month Year) 

  • Design began in January 2023.
  • Right-of-way acquisition is anticipated to begin in June 2024. 
  • Utility relocation is anticipated to begin in June 2024. 
  • Advertisement for construction is anticipated to begin in September 2024. 
  • Construction is anticipated to begin in December 2024. 

Contact Us

Charley Sessoms, PE
(804) 501-4687
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate