St. Claire Lane Sidewalk and Drainage Improvements

Project Status: Completed

Estimated Cost: $2.9 million
Start Date: September 2022
Estimated End Date: August 2023

Magisterial District:   Fairfield  


The County of Henrico will be constructing accommodation for pedestrian access and connectivity. The following improvements will be constructed, including: 

  • Approximately 2,400 linear feet of sidewalk, curb and gutter, and associated drainage infrastructure on St. Claire Lane located between the existing sidewalk on Mechanicsville Turnpike and Hollybrook Townhouses. 

Estimated Schedule: (Month Year) 

  • Design is complete.
  • Right-of-way acquisition completed.  
  • Utility relocation is not anticipated. 
  • Advertisement for construction is complete. 
  • Construction began September 2022.
  •  Project completed August 28, 2023. 

Progress to Date

  • citizen information meeting was held on February 26, 2018.
  • Pre-Construction meeting held September 9, 2022. 
  • Project is complete 7 photos of improvements beginning at Mechanicsville Turnpike extending to the cul-de-sac of St. Claire Lane.

Contact Us

LaTheasha Hinton
(804) 501-5115
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate