S. Laburnum Ave. Southbound Sidewalk

Project Status: Underway - Design

Estimated Cost: $2.9 Million
Start Date: March 2025
Estimated End Date: March 2026

Magisterial District:   Varina  


Approximately 3,100-ft of new sidewalk along the western side of S. Laburnum Avenue from 600-ft south of Gay Avenue to Williamsburg Road. Upgrades to existing transit bus stops within the project limits.  

Estimated Schedule: (Month Year) 

  • Design is underway. 
  • Right-of-way acquisition is anticipated to start January 2024. 
  • Utility relocation is anticipated to start February 2024. 
  • Advertisement for construction is anticipated January 2025. 
  • Construction is anticipated to commence March 2025. 

Progress to Date

  • Survey started March 13, 2023.

Contact Us

LaTheasha Hinton
(804) 501-5115
hin03@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon

Translate