Take a minute to get connected!

Tell us how you would like to receive Henrico County news and information

Pump Road Sidewalk Project

Project Status: Underway - Construction

Estimated Cost: $2.23 Million total
Start Date: May 2021
Estimated End Date: December 2021

Magisterial District:   Three Chopt  


The County of Henrico will be constructing pedestrian access along the east side of Pump Road from Hazel Tree Drive to Kingsbury Court.  The following improvements will be constructed, including: 0.44 miles of 5-foot sidewalk, 2-foot wide utility strip, road widening, curb and gutter and storm sewer on the east side of Pump Road from Kingsbury Court to Hazel Tree Drive

Estimated Schedule

  • Design began May 2018
  • Right-of-way acquisition began April 2019
  • Utility relocation began January 2020
  • Advertised for Construction January 2021
  • Construction is anticipated to begin in May 2021
  • Project completion is anticipated December 2021

Progress to Date

  • A Citizen Information Meeting was held on Monday, February 2019

Contact Us

Kevin Newcomb
(804) 501-5532
new038@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon