Project Status: Underway - Construction
Estimated Cost: $2.23 Million total
Start Date: July 2021
Estimated End Date: March 2022
Magisterial District: Three Chopt
The County of Henrico will be constructing pedestrian access along the east side of Pump Road from Hazel Tree Drive to Kingsbury Court. The following improvements will be constructed, including: 0.44 miles of 5-foot sidewalk, 2-foot wide utility strip, road widening, curb and gutter and storm sewer on the east side of Pump Road from Kingsbury Court to Hazel Tree Drive
Estimated Schedule
- Design began May 2018
- Right-of-way acquisition was completed May 2020
- Utility relocation was completed February 2021
- Advertised for Construction January 2021
- Construction began July 2021
- Project completion is anticipated March 2022
Progress to Date
- A Citizen Information Meeting was held on Monday, February 2019