Nuckols Rd Pedestrian Improvements

Project Status: Preliminary

Estimated Cost: $1.8 million
Start Date: June 2025
Estimated End Date: June 2025

Magisterial District:   Brookland  


Design and construct sidewalk on the north side of Nuckols Road between Springfield Rd and Capital One Way.  Work will include crosswalks and pedestrian signals at the Nuckols Road and Capital One Way intersection.  

Estimated Schedule: (Month Year) 

  • Design began in August 2023. 
  • Right-of-way acquisition is anticipated to begin in October 2024. 
  • Utility relocation is anticipated to begin in March 2025. 
  • Advertisement for construction is anticipated to begin in April 2025. 
  • Construction is anticipated to begin in June 2025. 

Contact Us

Charley Sessoms, PE
(804) 501-4687
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate