North Gayton Road Sidewalk Project

Project Status: Underway - Design

Estimated Cost: $1.24 Million total
Start Date: Spring 2019
Estimated End Date: Spring 2020

Magisterial District:   Three Chopt  


The County of Henrico will be constructing sidewalk along the west side of North Gayton Road, between Graham Meadows Drive and Causeway Drive

Estimated Schedule

  • Design is underway
  • Right-of-way acquisition is for anticipated Spring 2018
  • Utility relocation is anticipated for Fall 2018
  • Advertisement for Construction is anticipated Spring 2018
  • Construction is anticipated to begin in Spring 2019
  • Project completion is anticipated in Spring 2020

Progress to Date


Contact Us

Paul Smith
(804) 501-5092
smi91@henrico.us