Maude Trevvett Elementary Sidewalk Connection

Project Status: Underway - Design

Estimated Cost: $812,000
Start Date: May 2025
Estimated End Date: January 2026

Magisterial District:   Brookland   Fairfield  


The County of Henrico will be constructing the following improvements: 

  • Install approximately 450-ft of sidewalk and ADA ramps from Maude Trevvett Elementary School (Trevvett Drive) to Carter’s Bridge Place (east side of Woodman Road just south of E Parham Road). 

Estimated Schedule: (Month Year) 

  • Design began September 2022. 
  • Right-of-way acquisition is anticipated to begin March 2024 
  • Utility relocation is anticipated to begin June 2024
  • Advertisement for construction is anticipated February 2025. 
  • Construction is anticipated to begin May 2025 
  • Project completion is anticipated for January 2026. 

 

 

Contact Us

Kevin Newcomb
(804) 501-5532
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775