Magellan Parkway Extension
Project Status: Underway - Right of Way Acquisition
Estimated Cost: $14.4 million
Start Date: January 2024
Estimated End Date: November 2024
Magisterial District: Fairfield
The County of Henrico will be constructing a new access road to replace a two-lane segment of Scott Road with a combination of four-lane divided and three-lane roadway sections with raised medians, curb and gutter, and a 10’ shared use path. The roadway will extend approximately 2,350 linear feet. An intersection will be provided at Scott Road/Level Green Road. A roundabout will also be constructed for connections with a future north/south road. |
|||
Estimated Schedule: |
|||
|
Progress to Date
- Survey Completed
- 90% plans completed
- A public information meeting is scheduled for April 19, 2023 at North Park Library, 8508 Franconia Road, Henrico, VA 23227.