Laburnum Avenue Sidewalk Improvements

Project Status: Underway - Design

Estimated Cost: $834,000
Start Date: May 2021
Estimated End Date: November 2021

Magisterial District:   Fairfield  


The Laburnum Ave Sidewalk Improvements project consists of approximately 1,450 Feet of 5-foot sidewalk with ADA ramps on the north side of Laburnum Avenue between Mechanicsville Turnpike “Route 360” and Bolling Road in eastern Henrico County. The project also includes the installation of approximately 1,200 Feet of curb and gutter and associated drainage structures along this road segment.  

Estimated Schedule

  • Design is underway 
  • Right-of-way acquisition is anticipated to be complete February 2021
  • Utility relocation is anticipated to be complete February 2021
  • Construction is anticipated to begin May 2021
  • Project completion is anticipated to be complete November 2021

Contact Us

Michael Aust
(804) 501-4019
aus019@henrico.us


Public Works

Henrico Department of Public Works
4301 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon

Translate