E. Laburnum Avenue Sidewalk Improvements

Project Status: Underway - Design

Estimated Cost: $961,000
Start Date: May 2022
Estimated End Date: November 2022

Magisterial District:   Fairfield  


The County of Henrico will be constructing sidewalk along E. Laburnum Avenue.The following improvements will be constructed, including:

  • Approximately 1,450 feet of 5-foot sidewalk with ADA ramps on the north side of E. Laburnum Avenue between Mechanicsville Turnpike (Route 360) and Bolling Road..
  • The installation of approximately 1,200 feet of curb and gutter and associated drainage structures along this road segment.
  • Install transit amenities (concrete pad and bench) at each of the two GRTC bus stop locations.

Estimated Schedule

  • Design began in May 2018.
  • Right-of-way acquisition is anticipated to begin August 2020.
  • Utility relocation is anticipated to begin May 2021.
  • Advertisement for construction is anticipated February 2022.
  • Construction is anticipated to begin May 2022.
  • Project completion is anticipated November 2022

 

Progress to Date

  • Posted Notice of willingness to hold a public hearing July 2019. No comments were received.

Contact Us

Kevin Newcomb
(804) 501-5532
new038@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon

Translate