Hunton Park Boulevard Sidewalk

Project Status: Underway - Design

Estimated Cost: 610,000
Start Date: August 2021
Estimated End Date: December 2021

Magisterial District:   Brookland  


The County of Henrico will be constructing approximately 1,200 feet of 4-foot sidewalk. The sidewalk will connect directly to an existing 4-foot wide section of sidewalk located approximately 550 feet from the intersection of Staples Mill Road and Hunton Park Boulevard and ending at Hunton Park Lane with an ADA ramp. The sidewalk will include 5′ x 5′ pedestrian passing areas at reasonable intervals of approximately 200 feet. 

Estimated Schedule

  • Design began in April 2019
  • Right of Way acquisition began May 2020
  • Advertisement for Construction is anticipated in April 2021
  • Construction is anticipated to begin August 2021
  • Project completion is anticipated in December 2021

Progress to Date

 

  • The survey collecting comments is now closed, and the responses are being reviewed by County staff  as of September 9, 2017.  
  • A community meeting to present this project was held on August 16, 2017 at Glen Allen High School.  
  • The Real Property Division is preparing for easement acquisition

Contact Us

Conner Barnes
(804) 501-4244
bar136@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon

Translate