Gay Avenue Sidewalk Improvements
Project Status: Underway - Design
Estimated Cost: $900,000 total
Start Date: February 2020
Estimated End Date: August 2020
Magisterial District: Varina
The Gay Avenue Sidewalk Improvements project consists of approximately 1,600 linear feet of new sidewalk along the south side of Gay Avenue beginning 800 linear feet west of Laburnum Avenue where existing sidewalk terminates to Millers Lane. Approximately 130 linear feet of sidewalk will be constructed along the east side of Millers Lane south of Gay Avenue.
Estimated Schedule
- Design is underway
- Right-of-way acquisition is anticipated to be complete November 2019
- Utility relocation is anticipated to be complete November 2019
- Construction is anticipated to begin February 2020
- Project completion is anticipated to be complete August 2020