Fall Line Trail – Brook and Hilliard Road Phase

Project Status: Underway - Design

Estimated Cost: $6.86 million
Start Date: May 2025
Estimated End Date: April 2026

Magisterial District:   Fairfield  


The County of Henrico will be constructing approximately 2,800 linear feet of a minimum 12’ wide multi-use trail along with ADA compliant ramps along the north side of Hilliard Road and the west side of Brook Road from the northern end of the Lakeside Community Trail, Phase 3 to the intersection of Lakeside Avenue and Brook Road. This work will be a part of The Fall Line Trail, a 43-mile north-south paved trail that will connect Ashland to Petersburg.

 

Estimated Schedule: 

  • Design currently underway. 
  • Right-of-way acquisition is anticipated to start July 2023.  
  • Utility relocations are anticipated to start January 2024. 
  • Advertisement for construction is anticipated September 2024. 
  • Construction is anticipated to begin May 2025. 

 

Progress to Date

  • On Tuesday, May 16, 2023, the Henrico County Department of Public Works held a public information meeting from 5:00pm to 6:30pm at Lewis Ginter Botanical Gardens.  Materials from the meeting can be found in the Documents section below.  

Contact Us

Sarah Briggs
804-501-4616
bri114@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon

Translate