Creighton Road Sidewalk

Project Status: Underway

Estimated Cost: $510,000
Start Date: October 2019
Estimated End Date: Spring 2021

Magisterial District:   Fairfield  


This project involves the design and construction of approximately 1,100 feet of a new 5-foot wide sidewalk along the south side of Creighton Road between Harvest Crest Drive and Carolee Drive. The proposed sidewalk is to be constructed within existing right of way and maintain a 2-foot wide grass utility strip to match the existing sidewalk typical section along Creighton Road.

 

Project Schedule

  • Survey will begin in October 2019.
  • Right of Way acquisition is anticipated Summer 2020
  • Construction is anticipated Winter 2020