Creighton Road Improvements – Sandy Lane to Laburnum Avenue

Project Status: Underway - Utility Relocation

Estimated Cost: $13,048,474
Start Date: October 2022
Estimated End Date: October 2024

Magisterial District:   Fairfield   Varina  


The County of Henrico will be constructing the following improvements:

  • Realign the existing roadway to include a 0.4 mile 4-lane divided roadway with sidewalks on both sides of the road along with curb and gutter and storm sewer improvements. 
  • The road realignment includes relocating the Dabbs House Road intersection approximately 500 feet west of the current intersection, improving the intersection at Sandy Lane, and eliminating difficult to navigate curves in the roadway.

Estimated Schedule

  • Design is complete. 
  • Right-of-way acquisition completed June 2021. 
  • Utility relocation began July 2021. 
  • Advertisement for construction is anticipated July 2022. 
  • Construction is anticipated to begin October 2022. 
  • Project completion is anticipated October 2024. 

Progress to Date

  • A public hearing was held September 2014
  • The Creighton Road Bridge is complete as of March 3, 2017, and open for traffic.

Contact Us

Kevin Newcomb
(804) 501-5532
new038@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Category


 
Google Translate Icon

Translate