Creighton Road Improvements – Sandy Lane to Laburnum Avenue
Project Status: In Progress
Estimated Cost: $17.89 million
Start Date: March 2023
Estimated End Date: March 2025
Magisterial District: Fairfield Varina
The County of Henrico will be constructing the following improvements:
|
Estimated Schedule
- Design is complete.
- Right-of-way acquisition completed June 2021.
- Utility relocation completed April 2022.
- Advertisement for construction was completed January 2023.
- Construction started March 2o23.
- Project completion is anticipated March 2025.
Progress to Date
- A public hearing was held September 2014.
- The Creighton Road Bridge is complete as of March 3, 2017, and open for traffic.