Creighton Road Improvements – Sandy Lane to Laburnum Avenue
Project Status: Underway - Right of Way Acquisition
Estimated Cost: $12,575,670 total
Start Date: July 2022
Estimated End Date: July 2024
Magisterial District: Fairfield Varina
The County of Henrico will be constructing the following improvements:
|
Estimated Schedule
- Design is complete.
- Right-of-way acquisition completed June 2021.
- Utility relocation began July 2021.
- Advertisement for construction is anticipated April 2022.
- Construction is anticipated to begin July 2022.
- Project completion is anticipated July 2024.
Progress to Date
- A public hearing was held September 2014
- The Creighton Road Bridge is complete as of March 3, 2017, and open for traffic.