Take a minute to get connected!

Tell us how you would like to receive Henrico County news and information

Cobbs Creek Reservoir

Project Status: Underway - Construction

Estimated Cost: $280 million
Start Date: June 2017
Estimated End Date: Dec 2022

Magisterial District:   Project Located Outside of Henrico


Cobbs Creek Reservoir is the County’s $280 million project to secure its drinking water needs for perhaps the next five decades.  The Cobbs Creek Reservoir is a 14.8 billion-gallon regional water supply impoundment located in Cumberland County, Virginia that will augment the flow of the James River as needed.  Water will be pumped out of the reservoir and into the James River in the drier months, and it will be pulled from the James River into the reservoir in the wetter months.  The reservoir will help during drought or near drought conditions with providing extra water to the flow of the James River.

In exchange for the construction of the Cobbs Creek Reservoir, Virginia Department of Environmental Quality has approved an increase of the amount of raw water that Henrico County can take from the river each day to supply drinking water.  Previously, Henrico County could withdraw 45 million gallons per day on average.  Under the new approval, Henrico County can withdraw up to 75 million gallons per day on average.  These higher limits will allow Henrico to serve water customers as the county continues to grow for perhaps the next 50 years depending on the County’s rate of growth.

The facility creates an additional 17 million gallons per day approved by the Virginia Department of Environmental Quality available to Henrico and its regional partners.

Henrico has completed Phase I of the project, which was the acquisition of all the properties.  Staff from both Real Property and Public Utilities worked with 22 property owners to coordinate the purchase of the required property. 

Phase II of the project, where Colonial Pipeline Company and Dominion Energy relocated their existing utilities from the reservoir pool to outside the reservoir footprint, has also been completed.  During Phase II, DPU’s contractors also completed the construction of a communications tower and road system.

Phase III of the project began in October 2016 with the bidding process for the construction of the three earthen dams, the water intake structure in the James River, a pumping station, and other facilities which will support this massive operation. 

On March 2, 2017, sealed bids for the project were opened and read aloud by the County’s Purchasing Division.  After evaluating these and determining the lowest responsive and responsible bidder, the Board of Supervisors voted unanimously and awarded a contract for the construction of the reservoir to MEB Haymes Joint Venture LLC for $137.4 million on April 25, 2017.  This was lower than the design engineer’s estimate, and the seven bids received ranged from $137.4 million to $209.4 million.  MEB Haymes Joint Venture LLC is comprised of MEB General Contractors of Chesapeake and Haymes Brothers, Inc. of Chatham.

Construction on Cobbs Creek Reservoir began in June of 2017.  Since mobilizing the contractor has cleared areas of land to construct the access road to the pump station, the pump station site, and the soil borrow areas for the soils used to construct the dams (main, saddle and perimeter access road dams).  In addition, excavation of the pump station is complete.  The contractor has completed work in the two Intake Structures in the James River and begun removing the cofferdam in the James River.   They have completed the concrete and steel work at the pump station and will soon begin installing the roof.  The Quarry has been completed.  Work on the Perimeter Access Road Dam and Saddle Dam are about 95% complete.  The contractor has completed the grout curtain and slurry wall in the Main Dam.  The Energy Dissipator, Low Level Inlet and Spillway structures are also complete.  The concrete work for the Inlet/Outlet Tower is complete.  The contractor has completed placing the 72-inch piping from the drain valve vault (at the dam site) to the Pump Station.  The contractor continues working on the value vaults at the river site as well as the interior of the Pump Station and Operations Building and adding core and shell material lifts along the Main Dam footprint to within 45 feet of the top elevation of the dam. 

In total, there will be over 3.5 million cubic yards of soil excavated across the 1,117-acre site and used to build the three earthen dams.  The Perimeter Access Road Dam will be approximately 19 feet tall and the Saddle Dam will be about 25 feet tall and 1,200 feet long.  The larger Main Dam will stretch 3,850 feet in length along the north end of the reservoir and be 160 feet tall.  Additionally, there will be an intake structure with piping, a pump station, and an operations building all constructed by the James River to aid in the filling and draining of the reservoir.

Construction of this project is anticipated to be completed in approximately 5 years, and the reservoir is expected to be fully operational in 2023.

Updated:  5/27/2021

Progress to Date

Utility Clearing – Began in July 2015 and completed in February 2016
Utility Relocation – Began in March 2016 and completed in December 2016
Dam & Facilities Construction – Began in June 2017 with expected completion date in 2023


Contact Us

Emily McConnell
(804) 396-8519
mcc126@henrico.us


Public Utilities

Phone
(804) 501-4275
Phone After Hours (Emergency Only)
(804) 501-5025

utilities@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate