Church Road Sidewalk

Project Status: Underway - Design

Estimated Cost: $1.1 million
Start Date: July 2022
Estimated End Date: December 2022

Magisterial District:   Three Chopt  


The County of Henrico plans to construct sidewalk to increase pedestrian access and connectivity. The following improvements are planned to be constructed dependent on funding, including: 

  • Approximately 1800 feet of 5-foot wide concrete sidewalk on the west side of Church Road from Three Chopt Road to Morgan Run Road. 
  • Includes ADA ramps and connections to existing sidewalk. 
  • Construction Funding: Pending. Applied for Revenue Share grant. 

Estimated Schedule: 

  • Design is underway 
  • Right-of-way acquisition is anticipated to begin in April 2021. 
  • Utility relocation is anticipated to begin in February 2022. 
  • Advertisement for Construction is anticipated in February 2022. 
  • Construction is anticipated to begin in July 2022. 
  • Project completion is anticipated in December 2022. 

 

Contact Us

Sharon Smidler
(804) 501-4621
smi20@henrico.us


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

 
Google Translate Icon

Translate