Church Road Sidewalk Improvements
Project Status: Underway - Right of Way Acquisition
Estimated Cost: $510,100
Start Date: July 2023
Estimated End Date: April 2024
Magisterial District: Three Chopt
The County of Henrico plans to install sidewalk to increase pedestrian access and connectivity. The following improvements are planned:
- Construct approximately 1800 feet of 5-foot wide concrete sidewalk on the west side of Church Road from Three Chopt Road to Morgan Run Road.
- Provide ADA ramps and connections to new and existing sidewalk.
Estimated Schedule:
- Design is underway
- Right-of-way is underway.
- Utility relocation is not anticipated.
- Advertisement for construction is anticipated in May 2023.
- Construction is anticipated to begin in July 2023.
- Project completion is anticipated in April 2024.
A video with additional information on this project is below.
Progress to Date
- A virtual Public Information Meeting was held February 2022 and is posted on the County webpage.