Automated Traffic Management System (ATMS), Phase II
Project Status: Underway - Construction
Estimated Cost: $10.1 million
Start Date: June 2023
Estimated End Date: June 2024
Magisterial District: Brookland Fairfield Three Chopt Tuckahoe Varina
The County of Henrico will be upgrading their signal equipment. The following improvements will be constructed, including:
- Provide signal improvements / upgrades / rebuilds for numerous locations around Henrico County.
Estimated Schedule: (Month Year) |
|||
|
Progress to Date
- VDOT Authorization to Advertise received 1/3/2023.
- Looking to Advertise January 22, 2023. ITB to be submitted the week of 1/9/2023.
- 5 span wire project submitted to County Traffic for review. To be advertised separately.