John Rolfe Parkway Sidewalk

Project Status: Underway - Design

Estimated Cost: $540,000 total
Start Date: Winter 2017
Estimated End Date: 2017

Magisterial District:   Tuckahoe  


Henrico County is constructing approximately 0.70 mile of sidewalk on John Rolfe Parkway between Ridgefield Parkway and Gayton Road. The design will evaluate placement of a 5’ wide sidewalk or another acceptable alternative.  Crosswalk and pedestrian signals will be installed as part of the project.

Estimated Schedule

  • Design is  70% complete, and anticipated for completion September 2016
  • Right-of-way acquisition is anticipated to begin November 2016
  • Utility relocation is not anticipated for this project
  • Construction is anticipated to begin in February 2017
  • Project completion is anticipated in 2017

 

Progress to Date

  • Design is now 70% complete, and is expected to be fully complete by October 2016.
  • A Citizen Information Meeting for this project was held on October 14th, 2015. 

Contact Us

Public Works

Henrico Department of Public Works
4301 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775