Charles City Road Improvements

Project Status: Underway - Construction

Estimated Cost: $3.5 million total
Start Date: January 2017
Estimated End Date: October 2017

Magisterial District:   Varina  


This project will widen an approximately ¼ mile section of Charles City Road between Millers Road and Lisle Road to a four-lane divided facility with curb-and-gutter and drainage improvements.  The project also includes an upgraded railroad crossing at the CSX spur line with gates and flashing lights that will be coordinated with the traffic signal at the intersection of South Airport Drive.  Other components of the project include dual left-turn lanes for eastbound traffic entering the airport and a relocated entrance that includes a right-turn lane into the Dominion Power facility.

Estimated Schedule

  • Design is complete
  • Right-of-way acquisition is complete
  • Utility relocation began October 2015
  • Construction began January 2017
  • Project completion is anticipated  in October 2017

Contact Us

Margaret-Anne Hilliard
(804) 501-4244
hil66@henrico.us


Public Works

Henrico Department of Public Works
4301 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

DPW@henrico.us

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Category