Magellan Parkway Bridge over I-95 Section

Project Status: Underway - Utility Relocation

Estimated Cost: $34 million
Start Date: November 2024
Estimated End Date: October 2026

Magisterial District:   Fairfield  


The County of Henrico will be constructing a new access road consisting of a four-lane divided parkway with a raised median, curb and gutter, and a 10’ shared use path. The roadway will extend approximately 2,100 linear feet between Englewood Farms Drive to Scott Road and includes a bridge crossing over Interstate 95. 

 

Estimated Schedule: 

  • Survey and design are currently underway. 
  • Right-of-way acquisition is currently underway.
  • Utility relocation is currently underway. 
  • Advertisement for construction is anticipated in July 2024. 
  • Construction is anticipated to begin in November 2024. 
  • Project completion is anticipated in October 2026. 

Magellan Parkway I-95 Bridge and Extension Video

Progress to Date

  • A public information meeting was held April 19, 2023 from 5:30pm to 6:30pm at North Park Library, 8508 Franconia Road, Henrico, VA 23227.

Contact Us

Robert Whitaker III
(804) 727-8253
[email protected]


Public Works

Henrico Department of Public Works
4305 E. Parham Rd.
Henrico, VA 23228

Phone
(804) 501-4393

[email protected]

Mailing Address
P. O. Box 90775
Henrico, VA 23273-0775

Twitter Facebook

 
Google Translate Icon

Translate